Gladstone Footpaths

Project Name: Asphalt Overlay of Footpaths Project
Client: Gladstone Regional Council

Project Commencement Date: 3 June 2019
Project Completion Date: 13 June 2019
Project Budget: $500,000.00

ZAFA Contracting Pty Ltd was awarded the contract to undertake asphalt overlay works covering public use footpaths in Gladstone Regional Council controlled Parks and CBD. The project goal was to install a uniform surface to existing & new pedestrian access facilities to allow uninterrupted use by mobility assistance vehicles in conjunction with reducing existing trip hazards. Work crews utilised a combination of mobile plant & skilled hand labour to install 1000 + tonne of asphalt surface to 14 targeted areas.

 

Zafa Contracting coordinated asphalt crews, cartage, material supply & traffic/pedestrian management contractors to assist in completing the works package in a 14-day period, meeting practical completion targets without Quality, WH&S or Environmental incident.